The Wilshire widening gets the headlines, but it is not the only road work in Burleson. Here are the other projects with state filings or city budgets behind them, so you can plan your commute and your home search around them.
| Project | What | Dates on file |
|---|---|---|
| SH 174 (Wilshire Blvd.) | Four lanes to six, median, sidewalks, signals | Began Oct. 12, 2026; done in 2028 |
| I-35W at FM 917 | Interchange rebuild, Bethesda Rd. to Asher Rd., about $73.5M | July 2026 to Feb. 2029 |
| Village Creek Parkway | McCall St. to Alsbury Blvd. | Aug. 2026 to Feb. 2028 |
| Hulen Street | Widening from SH 174 to Candler, about $17.8M budgeted | City page estimated a Feb. 2026 start |
| FM 3391 | 2.83 miles from I-35W east of CR 602; two lanes to six (to S. Hurst) and four, about $80.6M | Feb. 2028 to June 2030 |
Dates come from Texas Department of Licensing and Regulation filings and city documents. They are estimates and can move.
Road work is temporary, and buyers know it. What hurts is surprise. If your street is affected, give buyers easy directions, and point out the long-term benefit: wider roads, sidewalks and safer intersections.
The full Wilshire story is in Wilshire is going to six lanes.
Projects include the SH 174 (Wilshire Blvd.) widening, the I-35W interchange rebuild at FM 917, Village Creek Parkway from McCall St. to Alsbury Blvd., Hulen Street widening, and the future FM 3391 widening.
The state filing lists the roughly $73.5 million project from Bethesda Rd. to Asher Rd. running from July 2026 to February 2029.
The state filing lists February 2028 to June 2030 for the 2.83-mile project east of I-35W.